The forward pass in project network calculations determines all of the following EXCEPT


A) Earliest time an activity can begin.
B) Earliest time an activity can finish.
C) Duration of the project.
D) The critical path.
E) How soon the project can finish.

F) C) and D)
G) A) and C)

Correct Answer

verifed

verified

The forward pass through a project network determines the critical path.

A) True
B) False

Correct Answer

verifed

verified

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as


A) Hammock.
B) Laddering.
C) Lag.
D) Cushion.
E) Buffer.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Which of the following can be used without coordinating with managers of succeeding activities?


A) Total slack
B) Free slack
C) Critical float
D) Float pad
E) Slip pad

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

Arrows on an activity-on-node (AON) project network represent


A) An activity.
B) Project flow.
C) Dependency.
D) Project flow and dependency.
E) An activity and dependency.

F) A) and C)
G) B) and C)

Correct Answer

verifed

verified

The activity time estimates used to build a project network are derived from ________.

Correct Answer

verifed

verified

work packages
Explanation: A work packag...

View Answer

An activity can include only one work package.

A) True
B) False

Correct Answer

verifed

verified

The amount of time an activity can be delayed and yet not delay the project is termed


A) Total slack.
B) Free slack.
C) Critical float.
D) Float pad.
E) Slip pad.

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select


A) The smallest LS of all its immediate successor activities to establish the LF.
B) The largest ES of all its immediate successor activities to establish the LF.
C) The average LS of all its immediate successor activities to establish the LF.
D) The smallest ES of all its immediate successor activities to establish the LF.
E) The largest LS of all its immediate successor activities to establish the LF.

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

A(n)_____________ calculates project duration.

Correct Answer

verifed

verified

forward pass
Explanation: The ...

View Answer

When completing a forward pass you carry the early finish to the next activity where it becomes its early start, unless the next succeeding activity is a merge activity.In this case you select the largest early finish number of all its immediate predecessor activities.Why do you select the largest early finish number?

Correct Answer

verifed

verified

Acknowledging that the finish number rep...

View Answer

Which of the following is provided by both the project network and the work breakdown structure?


A) Dependencies
B) Sequencing
C) Interrelationships
D) Activity duration
E) Timing

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

The delaying of any activity on the __________ will delay the completion of the project by the same amount.

Correct Answer

verifed

verified

critical path
Explanation: Cri...

View Answer

The _________ lag is the most typical type of lag that is encountered in developing networks.

Correct Answer

verifed

verified

finish to start
Explanation: The finish-...

View Answer

A(n)__________ activity is frequently used to identify the use of fixed resources or costs over a segment of the project.

Correct Answer

verifed

verified

hammock
Explanation: Hammock activities ...

View Answer

Within an Activity-on-Node network, the arrows depict activities to be accomplished.

A) True
B) False

Correct Answer

verifed

verified

Briefly describe looping and conditional statements and explain why they are not allowed when developing project networks.

Correct Answer

verifed

verified

Looping is the attempt by the network de...

View Answer

Activities that must immediately follow a given activity are called ________ activities.

Correct Answer

verifed

verified

successor
Explanation: Activit...

View Answer

Which of the following is true about hammock activities?


A) They are used to identify the use of fixed resources or costs over a segment of a project.
B) They are a combination of Start to Start and Start to Finish lags.
C) They are activities in which the costs are not subject to change.
D) They are an alternative description for the critical path.
E) They are highly sensitive.

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

___________ reflects the likelihood the original critical path(s)will change once the project is initiated.

Correct Answer

verifed

verified

Sensitivity
Explanation: Sensitivity ref...